Titanium Valley's natural gas pipeline nears completion

Last week, the Sverdlovsk Region Press Service and Information Administration announced that the high-pressure natural gas pipeline at the Titanium Valley Special Economic Zone will soon be completed.

In total, the pipeline measures 5.1 miles from its entry point at the Verkhnyaya Salda to its connection at Titanium Valley, Ural Business Consulting reports.

Currently, crews are at work testing the welding and connection quality of the pipeline and planning the final stages of assembly prior to the pipeline's opening, which is scheduled for July.

Once the pipeline is complete, Titanium Valley's developers will begin construction on the zone's electricity, gas, water and heating systems. The pipeline will supply gas to locals and businesses in the region, according to Ural Business Consulting.